| Lessons Learned - Log
|
Add New Entry |
Status | 20 | Date | 19-06-2020 | Name | James Cotty | Experience Type (+/-) | Negative | Actions |
Subject | Component B not fitting to C as desired | EditDelete | ||||||
Comments | First-off parts show interfaces of parts to each other are NOK | |||||||
Recommendations | CAD simulation showed no issues, but first parts NOK. In future sample parts must be sought in early development phases | |||||||
Status | 20 | Date | 19-06-2020 | Name | James Cotty | Experience Type (+/-) | Negative | Actions |
Subject | Component B not fitting to C as desired | EditDelete | ||||||
Comments | First-off parts show interfaces of parts to each other are NOK | |||||||
Recommendations | CAD simulation showed no issues, but first parts NOK. In future sample parts must be sought in early development phases | |||||||
Status | 20 | Date | 30-06-2020 | Name | James Cotty | Experience Type (+/-) | Negative | Actions |
Subject | Component A development has taken far longer than planned | EditDelete | ||||||
Comments | Development went on way past time line as Engineering did not have a full specification from Design. But Design say they hadn't seen sample parts to base a decision on. | |||||||
Recommendations | Design should be able to source sample parts earlier in the process. | |||||||
Status | 20 | Date | 30-06-2020 | Name | James Cotty | Experience Type (+/-) | Negative | Actions |
Subject | Component A development has taken far longer than planned | EditDelete | ||||||
Comments | Development went on way past time line as Engineering did not have a full specification from Design. But Design say they hadn't seen sample parts to base a decision on. | |||||||
Recommendations | Design should be able to source sample parts earlier in the process. | |||||||
Status | 20 | Date | 15-06-2020 | Name | James Cotty | Experience Type (+/-) | Positive | Actions |
Subject | Supplier really easy to work with and understood expected work almost immediately | EditDelete | ||||||
Comments | Supplier was able to follow expectations from the start. Helped by a having done the work before and having pre-conversations up front to help guide the specification. | |||||||
Recommendations | Talk to suppliers as early as possible to include them in the early design phases as they understand the technologies trying to be implemented. | |||||||
Status | 20 | Date | 15-06-2020 | Name | James Cotty | Experience Type (+/-) | Positive | Actions |
Subject | Supplier really easy to work with and understood expected work almost immediately | EditDelete | ||||||
Comments | Supplier was able to follow expectations from the start. Helped by a having done the work before and having pre-conversations up front to help guide the specification. | |||||||
Recommendations | Talk to suppliers as early as possible to include them in the early design phases as they understand the technologies trying to be implemented. | |||||||